Estimate labour hours where the work happens
Do not bury labour in one blended number. Assign hours to the stations that will do the work: engineering and detailing, programming or layout, cutting, forming, welding, grinding, finishing, panel assembly, ceiling or lighting assembly, quality inspection, packing, delivery, and installation. Use the stations on your shop floor.
For each station, record planned hours, crew assumptions, setup time, repeated-unit learning where your approved method permits it, and your shop's approved hourly rate. Keep premium time, travel, supervision, and restricted jobsite hours separate. The same hour structure later supports capacity planning; the project stages guide explains that production gate.
Know when a BOM line needs a vendor quote
Use catalogue or approved rate-library pricing for repeatable standard items only when the source, effective date, unit, and purchasing conditions are controlled. Get a vendor quote for custom fabrication, specialty finishes, glass, stone, unique hardware, outsourced processes, and anything with uncertain delivered cost or lead time.
Store the vendor quote with the estimate. Record its expiration, minimum order, tooling, setup, freight, applicable taxes, exclusions, submittal requirements, and lead time. If it will expire before likely release, say so. An unexplained contingency is not a substitute for a missing quote.
Freight, site access, and contingency
Freight is more than one carrier line. Include inbound supplier freight, dedicated or consolidated shop-to-site delivery, fuel or access charges where quoted, crating, unloading, hoisting, storage, redelivery, and protection. Confirm dock size, street restrictions, delivery windows, floor path, service-elevator availability, security, and work-hour rules.
Contingency belongs against named uncertainty. Incomplete survey dimensions, unsettled finishes, volatile supply, compressed review periods, or difficult access may justify an allowance under your shop's policy. Identify what it covers. Keep exclusions explicit. Do not invent a universal percentage.
Re-price the drawing delta, not the whole job
Freeze the quoted baseline: scope, revision, BOM, station hours, vendor support, logistics, assumptions, and price. When a site survey or drawing comment changes material, quantity, finish, geometry, labour, freight, access, or schedule, compare the new condition with that baseline line by line.
That delta becomes the final estimate or change order. Show additions, credits, lead-time effect, and the revision that caused each change. Get the required approval before a buyer places an order or the shop starts fabrication. The submittal approval guide explains how Final for Record establishes the controlled production scope.