Estimate labour hours by station
Do not hide labour in one blended number. Break it into engineering and detailing, programming or layout, cutting, forming, welding, grinding, finishing, panel assembly, ceiling or lighting assembly, quality inspection, packing, delivery, and installation. Use the stations that match your shop.
For each station, record planned hours, crew assumptions, setup time, repeated-unit learning where your approved method permits it, and your shop's approved hourly rate. Separate premium time, travel, supervision, and restricted jobsite hours. The same hour structure later supports capacity planning; the project stages guide explains that production gate.
Vendor quote versus catalogue pricing
Catalogue or rate-library pricing fits repeatable standard items when the source, effective date, unit, and purchasing conditions are controlled. Vendor quotes belong on custom fabrication, specialty finishes, glass, stone, unique hardware, outsourced processes, and any item with uncertain delivered cost or lead time.
Store the quote with the estimate. Capture expiration, minimum order, tooling, setup, freight, taxes where applicable, exclusions, submittal requirements, and lead time. If the quote expires before likely release, state the exposure. Never replace a missing quote with unexplained contingency.
Freight, site access, and contingency
Freight is more than one carrier line. Include inbound supplier freight, dedicated or consolidated shop-to-site delivery, fuel or access charges where quoted, crating, unloading, hoisting, storage, redelivery, and protection. Confirm dock size, street restrictions, delivery windows, floor path, service-elevator availability, security, and work-hour rules.
Contingency belongs against named uncertainty. Incomplete survey dimensions, unsettled finishes, volatile supply, compressed review periods, or difficult access may justify an allowance under your shop's policy. Identify what it covers. Keep exclusions explicit. Do not invent a universal percentage.
The re-price trigger after engineering
Freeze the quoted baseline: scope, revision, BOM, station hours, vendor support, logistics, assumptions, and price. When survey findings or drawing comments change material, quantity, finish, geometry, labour, freight, access, or schedule, compare the revised condition line by line.
That delta becomes the final estimate or change order. Include additions, credits, lead-time effect, and the revision that caused them. Obtain required approval before purchase or fabrication. The submittal approval guide explains how Final for Record establishes the controlled production scope.